PMP Questions and Answers

Free PMP Questions and Answers – Are You Ready for PMP Exam?26 min. read

PMP is the world’s most prestigious certification in project management field. PMP certification exam has 200 questions and requires a good PMP study plan to pass the exam successfully. One of the 7 steps for passing PMP certification is making practice with free PMP questions and answers before the exam.

When practicing free PMP questions and answers, take notes especially for the mistakes you make. Then, go back to the related project management knowledge area and reread the topic to strengthen your knowledge. That is the only way to grab all you need to know for each project management processes you will see in the PMP Exam.


After helping over 50,000 professionals in more than 180 countries with a 99.6% first attempt pass rate, we have prepared a seven-step PMP study plan. Read this PMP study plan and create your own PMP prep plan accordingly.


PMP Exam Questions Change in Dec 15, 2019

PMI make industry research regularly and adapts the PMP certification exam accordingly based on the changing industry dynamics. For instance, more than 10 years ago, most of the corporate organizations were preferring waterfall project management methodology. However, most of the organizations shifting agile methodologies in recent years.

Based on the changing industry dynamics and what organizations expect from project managers, PMI will be changing PMP exam in 2019 as well. We have prepared a detailed post about what is changing in PMP exam and how you should be prepared for the changes. If you are looking to get your PMP certification, it is better to get it before the next PMP exam changes.

Free PMP Questions and Answers – 40 Questions

We will go through 40 Free PMP questions and answers in this post. We will be giving rationales for each free PMP questions and answers. You will see the relationship of each PMP questions and answers with the project management knowledge areas of PMBOK.

Free PMP questions and answers

PMP Questions and Answers #1

A manager and the head of engineering discuss a change to a major work package. After the meeting, the manager contacts you and tells you to complete the paperwork to make the change. This is an example of:

A-) Management attention to scope management.

B-) Management planning.

C-) A project expediter position.

D-) A change control system.

 

Answer is C. In this situation, project manager acts as the secretary of the project and does the paper work. So this is an example of project expediter position where project manager does not have any authority and power. Project manager does only paper work.

Knowledge Area: Organizational Influences and Project Lifecycle

PMP Questions and Answers #2

During a team meeting, a team member asks about the measurements that will be used on the project to judge performance. The team member feels that some of the measures related to activities assigned him are not valid measurements. The project is BEST considered in what part of the project management process?

A-) Initiating

B-) Executing

C-) Monitoring & Controlling

D-) Closing

Answer is B. Executing. Questions states that team member feels some of the measures on his activities are not valid. Therefore, he must be working during the executing phase of the project where project deliverables are produced and project members perform most of the work they should do.

Knowledge Area: Project Management Processes

PMP Questions and Answers #3

Your company just won a major new project. It will begin in three months and is valued at 2m USD. You are the project manager for an existing project. What is the FIRST thing you should do once you hear of the new project?

A-) Ask management how the new project will use resources

B-) Resource level your project

C-) Crash your project

D-) Ask management how the new project will affect your project

Answer is D. Ask management how the new project will affect your project. Since this is another project that your company is going to execute, you need to be sure whether it will impact your project.

Knowledge Area: Integration Management Knowledge Area

PMP Questions and Answers #4

You are a new project manager who has never managed a project before. It would be BEST in this situation to rely on _____ during planning in order to improve your chance of success.

A-) Your intuition and training

B-) Stakeholder analysis

C-) Historical information

D-) Configuration management

Answer is C. Historical information. First thing to explore before starting a new project is the historical information about similar projects in the organizational process assets library of the organization.

Knowledge Area: Integration Management Knowledge Area


 

If you are looking for a PMP training with thousands of PMP practice questions PMP Certification Online Course bundle will be a good option. The most comprehensive PM training bundle of Master of Project Academy is Project Management Training program.

 


PMP Questions and Answers #5

During project executing, a team member comes to the project manager because he is not sure of what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of work packages?

A-) WBS Dictionary

B-) Activity List

C-) Project scope statement

D-) Scope management plan

Answer is A. WBS Dictionary. Work packages in a Work Breakdown Structure contain only nouns or a couple of words regarding a work or deliverable. Detailed information on what needs to be done, responsible, prerequisites, successors, due date etc. are included in the Work Breakdown Structure Dictionary.

Knowledge Area: Scope Management Knowledge Area

Enroll in our PMP Exam Simulator to access over 1,400 PMP questions and answers. You can see the demo of the PMP exam simulator here: Free PMP Exam Simulator.

PMP exam simulator

 

PMP Questions and Answers #6

During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by these stakeholders. The BEST thing for the project manager to do is to:

A-) Let the sponsor know of the stakeholders’ request.

B-) Evaluate the impact of adding the scope.

C-) Tell the stakeholders the scope cannot be added.

D-) Add the work if there is time available in the project

schedule

Answer is C. Tell the stakeholders the scope cannot be added. After the scope of a project is finalized and scope baseline is determined, it can be changed only with the approved changed requests. If there is not an approved change request, existing scope baseline must be valid and project team must work on to deliver that scope only. In the scenario, scope is defined already but some stakeholders ask to add new work to the scope. This cannot be done unless there is an approved change request. Therefore, stakeholders must be informed that this new work cannot be added.

Knowledge Area: Scope Management Knowledge Area

PMP Questions and Answers #7

Your project management plan results in a project schedule that is too long If the project network diagram cannot change but you have extra personnel resources, what is the BEST thing to do?

A-) Fast track the project.

B-) Level the resources.

C-) Crash the project.

D-) Monte Carlo analysis.

The answer is C, crash the project. Because, in first sentence, it is mentioned that schedule is too long, therefore the aim is making a shorter schedule. And in the second sentence it is mentioned that you have extra personnel resources. If you have resources, you can put more resources in an activity to complete it in a shorter time. And this is actually a description of crashing an activity or crashing the project. If you look to the other options, fast tracking was performing activities in parallel instead of series, therefore it is irrelevant. Leveling the resources was for fixing the over-allocation of resources and distributing the tasks to all your resources uniformly. And Monte Carlo analysis was another estimating tool which is irrelevant choice as well. Therefore, here the best answer is C.

Knowledge Area: Schedule Management Knowledge Area

PMP Questions and Answers #8

An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9, and a late finish (LF) of day 19. The activity:

A-) Is on the critical path.

B-) Has a lag.

C-) Is progressing well.

D-) Is not on the critical path.

Answer is D. is not on the critical path. Because if you look to the early start and late start values of the activity, you can find the float or the slack of activity’s time by subtracting early start, 3 days, from the late start, 13 days. And it gives 10 days of float for this activity. You will find the same result if you go through subtracting the early finish, 9 days, from the late finish, 19 days. Since the float of activity or the slack of the activity is greater than zero, it’s not on the critical path. Remember the critical path activities was having zero float, therefore the answer is D.

Knowledge Area: Schedule Management Knowledge Area

PMP Questions and Answers #9

Early in the life of your project, you are having a discussion with the sponsor about what estimating techniques should be used. You want a form of expert judgment, but the sponsor argues for analogous estimating. It would be BEST to:

A-) Agree to analogous estimating, as it is a form of expert judgment

B-) Suggest life cycle costing

C-) Determine why the sponsor wants such an accurate estimate

D-) Try to convince the sponsor to allow expert judgment because it is typically more accurate.

Answer is A. Agree to analogous estimating, as it is a form of expert judgment. Since analogous estimating is a type of expert judgment you can accept it. This is a tricky question.

Knowledge Area: Cost Management Knowledge Area

PMP Questions and Answers #10

A schedule performance index, SPI, of 0.75 means:

A-) Project is over budget.

B-) Project is ahead of schedule.

C-) Project is progressing at 75% of the rate originally planned

D-) Project is progressing at 25% of the rate originally planned

Answer is C, project is progressing at 75% of the rate originally planned. A, is irrelevant because SPI is a schedule performance index. We cannot derive any conclusion about budget performance of the project with this index. B, is not correct because SPI is less than one, therefore, the project is behind schedule. And D, says that you have completed 25% of the work that you have originally planned, so it’s not correct. The correct answer here is C, because SPI 0.75 means, you have completed 75% of your work that you have originally planned.

Knowledge Area: Cost Management Knowledge Area


Enroll in our FREE PMP course to learn more about PMP Certification


PMP Questions and Answers #11

You are the program level manager with several project activities underway. In the executing process group, you begin to become concerned about the accuracy of progress reports from the projects. What would BEST support your opinion that there is a problem?

A-) Quality Audits

B-) Risk Quantification Reports

C-) Regression Analysis

D-) Monte Carlo Analysis

Answer is A. quality audits. If you read the second sentence again, it says that you are concerned about the accuracy of progress reports from the project. In order to check whether the standards of your organization have been applied in the projects that you are responsible of, you can conduct a quality audit and find out whether there is really a problem. Therefore, here the best answer is A, Quality Audits.

Knowledge Area: Quality Management Knowledge Area

PMP Questions and Answers #12

You are a project manager for a major information systems project. Someone from the quality department comes to see you about beginning a quality audit of your project. The team, already under pressure to complete the project as soon as possible, objects to the audit. You should explain to the team that the purpose of a quality audit is:

A-) Part of an ISO 9000 investigation

B-) To check if the customer is following its quality process

C-) To identify inefficient and ineffective policies

D-) To check the accuracy of costs submitted by the team

How would you explain it to your team if you were in this case? The best answer is C, to identify inefficient and ineffective policies. B and D are irrelevant options because quality audit is done in order to check whether you are meeting the quality standards, whether you are following the quality procedures of your company. Therefore, it’s not related whether the customer is following its quality processes. Or it is not related about accuracy of costs submitted by the team.

Knowledge Area: Quality Management Knowledge Area

PMP Questions and Answers #13

During every project team meeting, the project manager asks each team member to describe the work he or she is doing, and the project manager assigns new activities to team members. The length of these meetings has increased because there are many different activities to assign. This could be happening for all the following reasons EXCEPT:

A-) Lack of a WBS

B-) Lack of a responsibility assignment matrix

C-) Lack of resource leveling

D-) Lack of team involvement in project planning

Answer is C, lack of resource leveling. If you read the clauses again, here the problem is the activities or the tasks that need to be performed in the project are not clear. So, the reasons of these ambiguities, or these unclear points about the tasks that will be performed can be lack of a WBS. If you could not decompose your project activities and creation of WBS, then this might be causing the ambiguities in your project tasks. Also, if you do not have a clear and concise responsibility assignment matrix, then the resources of your project will have unclarity about who will do what in the project. Also, if the team was not involved in project planning, maybe you could not have identified the required steps, required tasks, activities that need to be performed in the project. So, options A, B, and D are the possible reasons for this case mentioned in the question. However, lack of resource leveling might be causing a scheduling problem. Resource leveling is a technique used in schedule management knowledge area, which was enabling the uniform distribution of tasks and activities in a project.

Knowledge Area: Resources Management Knowledge Area

PMP Questions and Answers #14

Conflict resolution techniques that may be used on a project include confronting, smoothing, forcing, and:

A-) Withdrawing

B-) Directing

C-) Organizing

D-) Controlling

Which of the options is a conflict resolution technique? Answer is A, Withdrawing, or in other words, avoiding. The other three are directing, organizing, and controlling, are not types of conflict resolution techniques. Therefore, the answer is A.

Knowledge Area: Resources Management Knowledge Area

PMP Questions and Answers #15

All of the following about communication models is true EXCEPT:

A-) Sender encodes his thoughts and sends to receiver.

B-) Information is sent by the sender to receiver with the assistance of medium.

C-) Receiver acknowledges if he agrees with the information he received.

D-) Message is decoded by the receiver into thoughts.

Which one is not correct about communication models? The answer is C, Receiver acknowledges if he agrees with the information he received. If you remember, acknowledgement was saying that the receiver got the message, but it does not mean that he or she agrees with the received message. Acknowledgement means only that the message sent by the other party has been received. Therefore, it does not mean an agreement, and here the best answer is C.

Knowledge Area: Communications Management Knowledge Area

PMP Questions and Answers #16

A project manager is quantifying risk for her project. She needs expert opinion in this process and related experts are spread over to different geographical locations. How can she continue?

Using Monte Carlo analysis online

Applying the critical path method

Determine options for recommended corrective action

Applying the Delphi Technique

Answer is D, applying the Delphi Technique. If you remember from our previous lectures, that technique was asking the experts opinion on a topic or on a problem and collecting their feedback anonymously and then sending back the results back to the experts again, and recollecting their responses again. And reiterating this process until a consensus is reached by all participants, by all experts. Therefore, since expert opinion is important for this case and experts are spread over different geographical locations, we can use Delphi Technique.

Knowledge Area: Risk Management Knowledge Area

PMP Questions and Answers #17

During risk management activities, 236 risks have been identified which are caused by 13 root causes. You could eliminate the 234 risks by your risk management activities. For remaining 2 risks, you, together with your team, could not find a way to mitigate or insure the risks. Also these 2 risks cannot be outsourced or removed from project scope. What is the best solution?

A-) Accept the risk

B-) Mitigate the risk

C-) Avoid the risk

D-) Transfer the risk

Answer is A, accepting the risk. When you read the case, the project manager tried first to eliminate the risk, then tried to mitigate or insure the risk. But all these options did not work. And the last step is the risk should be accepted by the project team and continuous reserves should be allocated in order to accommodate risks or in order to overcome the bad impacts of these risks when they occur. Therefore, the best answer here is accepting the risk and also planning contingency reserves.

Knowledge Area: Risk Management Knowledge Area

PMP Questions and Answers #18

The project team is arguing about the prospective sellers who have submitted proposals. One team member argues for a certain seller while another team member wants the project to be awarded to a different seller. The BEST thing the project manager should remind the team to focus on in order to make a selection is the:

A-) Procurement documents

B-) Procurement audits

C-) Evaluation criteria

D-) Procurement management plan

Answer is C, evaluation criteria. The source selection criteria, or evaluation criteria defined in plan procurement management process actually defines, in an objective way, how quantitatively, the potential sellers will be evaluated in conduct procurements process. Therefore, if you have applied specific metrics, specific categories to evaluate, or assess a potential seller in conduct procurement process, then you have to use that metrics, use that categories to evaluate each seller one by one. And the sellers, which got the highest scores should be awarded with contract. Therefore, the team members should not go in argument about the selection of the sellers. Because you have already a quantitative metric to evaluate which seller is best matching to your source selection criteria.

Knowledge Area: Procurement Management Knowledge Area

PMP Questions and Answers #19

A project manager is in the middle of creating a request for proposal (RFP). What part of the procurement process is she in?

A-) Conduct procurements

B-) Plan Procurements

C-) Control Procurements

D-) Close Procurements

Answer is B, she is in plan procurements process. Because procurement statement of work, procurement documents are prepared in plan procurements management process. And RFP is a procurement document as well. Therefore, it is prepared in plan procurements process. RFP was defining what the buyer is requiring from the seller.

Knowledge Area: Procurement Management Knowledge Area

PMP Questions and Answers #20

You want to group your project stakeholders based on their authority and involvement in the project. Which of the following is appropriate model for this?

A-) Power/Interest Grid

B-) Power/Influence Grid

C-) Influence/Impact Grid

D-) Salience Model

Answer is B. Power/Influence Grid. Authority of a stakeholder represents power of the stakeholder and involvement of a stakeholder represents the influence level of the stakeholder. Therefore, answer is B. Power/Influence Grid.

Knowledge Area: Stakeholder Management Knowledge Area

PMP Exam Questions #21

Which of the following is NOT true for a project?

A-) Projects are constrained by limited resources

B-)Projects are planned, executed, and controlled

C-) Projects create a unique product or service

D-) Projects are ongoing and repetitive

Answer is D. A project is a temporary endeavor undertaken to create a unique product, service, or result. The temporary nature of projects indicates a definite beginning and ending.

Knowledge Area: N/A (Introduction)

PMP Exam Questions #22

In the context of a desirable model of communication between a sender and a receiver, all the following statements are correct EXCEPT:

A-) Noise should be at minimum level.

B-) Receiver must reply the message after decoding the message.

C-) Receiver should acknowledge first and then agree with the message sent by the sender.

D-) Receiver should send a feedback message to the sender.

Answer is C. As part of the communications process, the sender is responsible for the transmission of the message, ensuring the information being communicated is clear and complete, and confirming the communication is correctly understood. The receiver is responsible for ensuring that the information is received in its entirety, understood correctly, and acknowledged or responded to appropriately. However, receiver may not agree on received message

Knowledge Area: Communications Management

PMP Exam Questions #23

John is a project manager of a complicated project. When he started creating a work breakdown structure for his project, he realized that it is too complex to complete work breakdown structure on a single sheet. You, as a colleague of John, recommend using a work breakdown structure numbering system to John to:

A-) Determine the complexity of the project

B-) Help in automating the WBS using appropriate software

C-) Provide a hierarchical structure for each WBS element

D-) Present risks of the project

Answer is C. The WBS is finalized by assigning each work package to a control account and establishing a unique identifier for that work package from a code of accounts. These identifiers provide a structure for hierarchical summation of costs, schedule, and resource information.

Knowledge Area: Scope Management

PMP Exam Questions #24

You are trying to establish a cost performance baseline for your project in Determine Budget Process. You can use the following tool and techniques EXCEPT:

A-) Cost aggregation

B-) Bottom-up estimating

C-) Expert judgment

D-) Historical relationships

Answer is B. Tools and techniques used in Determine Budget Process are:

  • Cost aggregation
  • Reserve analysis
  • Expert judgment
  • Historical relationships
  • Funding limit reconciliation

Bottom-up estimating is used in Estimate Costs Process.

Knowledge Area: Cost Management

PMP Exam Questions #25

Which of the following techniques includes measuring, examining and validating whether work and deliverables meet requirements and product acceptance criteria?

A-)Workshops

B-)Surveys

C-)Expert Judgment

D-)Inspection

Answer is D. Inspection includes activities such as measuring, examining, and validating to determine whether work and deliverables meet requirements and product acceptance criteria.

Knowledge Area: Scope Management


Enroll in our FREE PMP Overview training to learn more about PMP Certification, and how to apply for PMP step-by-step.


PMP Exam Questions #26

You are a project manager in a bicycle manufacturing company. Rubber for brake mechanism for your bicycles supplied by RuBrake Inc could not reach due to flood affected the transportation routes. This was a risk you thought it could happen since it happens each year on same season. So, as per your risk response plan, you started to use rubbers delivered one year ago. However, this response brought another risk –old rubbers have higher breaking risk during implementation to the brake system.This new risk can also be called:

A-)Secondary risk

B-)Residual risk

C-)Contingency plan

D-)Unmanageable risks

Answer is A. Secondary risks are risks that arise as a direct result of implementing a risk response

Knowledge Area: Risk Management

PMP Exam Questions #27

All of the following are hygiene factors according to Herzberg’s Theory EXCEPT:

A-)Salary

B-)Professional Growth

C-)Security

D-)Relationships at work

Answer is B. According to Herzberg’s Theory, there are hygiene factors and motivating agents. Inadequate Hygiene factors may destroy motivation but sufficient hygiene factors itself are not enough to motivate people. Hygiene factors are:

  • Working card
  • Salary
  • Personal Life
  • Relationships at work
  • Security
  • Status

Professional growth is a motivating agent based on Herzberg’s Theory.

Knowledge Area: Resources Management

PMP Exam Questions #28

You are expected to manage stakeholders’ expectations as a project manager. All of the following are interpersonal skills that you should apply EXCEPT:

A-)Building trust

B-)Resolving conflict

C-)Risk taking

D-)Active listening

Answer is C. The project manager applies interpersonal skills to manage stakeholder’s expectations. For example:

  • Building trust
  • Resolving conflict
  • Active listening
  • Overcoming resistance to change

Knowledge Area: Stakeholder Management

PMP Exam Questions #29

There has been several changes in your project and this affected your cost and schedule estimates. This has invalidated the original estimating assumptions. What is the estimate at completion (EAC) for your project based on following parameters?

  • BAC = $ 360,000
  • AC = $ 120,000
  • EV = $ 180,000
  • CPI = 1.2
  • ETC = $ 145,000

A-)$ 300.000

B-)$ 265.000

C-)$ 325.000

D-)$ 360.000

Answer is B. EAC = AC + ETC = $ 120.000 + $ 145.000 = $ 265.000

Knowledge Area: Cost Management

PMP Exam Questions #30

Portfolio managers are responsible of managing:

A-)Dependency of different projects

B-)Operational projects only

C-)Projects, programs and operations

D-)Functional work and projects

Answer is C. The relationship among portfolios, programs, and projects is such that a portfolio refers to a collection of projects, programs, sub-portfolios, and operations managed as a group to achieve strategic objectives.

Knowledge Area: Introduction

PMP exam simulator

PMP Exam Questions #31

Your Company has entered into a joint venture with Service Company to develop a software program. Which of the following should be cooperatively prepared by both the buyer and the seller during teaming agreement process?

A-)Contract

B-)Contract, Procurement statement of work

C-)Request for proposal

D-)Human Resource Plan

Answer is B. In some cases, the seller may already be working under a contract funded by the buyer or jointly by both parties. The effort of the buyer and seller in this process is to collectively prepare a procurement statement of work that will satisfy the requirements of the project. The parties will then negotiate a final contract for award.

Knowledge Area: Procurement Management

PMP Exam Questions #32

There are three projects that are possible to be executed in your company:

  • Project A: Payback period= 6 years & NPV =$ 3,000,000
  • Project B: Payback period=4 years & NPV =$ 2,000,000
  • Project C: Payback period=2 years &NPV =$ 1,000,000

Based on Net Present Value (NPV) criterion, which project should be selected?

A-)Project A

B-)Project B

C-)Project C

D-)None of them, they all have equal value

Answer is A. Project A has highest NPV of $ 300,000. Time value of money is already taken into account when calculating NPV of a project. Since Project A has the highest NPV, it should be selected.

Knowledge Area: N/A

PMP Exam Questions #33

You are trying to gather ideas related to project and product requirements. Which technique is appropriate for this?

A-)Brainstorming

B-)Nominal Group Technique

C-)Affinity Diagram

D-)Multi-criteria Decision Analysis

Answer is A. A technique used to generate and collect multiple ideas related to project and product requirements.

Knowledge Area: Scope Management

PMP Exam Questions #34

Your colleague Wayne, a project manager, completed a mp3 player development project. While he was telling his experiences from his project, he mentioned that they delivered “adjustable screen timeout duration” feature, without a deviation from the plan, although the customer did not require and was not in scope of the project. He added that customer was very surprised and happy when they saw this additional feature at the end of the project. Which of the following is correct about this story?

A-)Gold plating was done in the project

B-)Customer satisfaction increased with an additional feature which they did not expect

C-)Change request has been delivered successfully

D-)Unnecessary risk has been taken by adding a new feature to product.

Answer is A. Gold plating refers to continuing to work on a project or task well past the point where the extra effort is worth the value it adds (if any). After having met the requirements, the assignee works on further enhancing the product, thinking the customer would be delighted to see additional or more polished features, rather than what was asked for or expected.

Knowledge Area: N/A

PMP Exam Questions #35

You have documented all possible risks that can affect your project with appropriate risk responses when they occur in your risk management plan. All other remaining risks are called as:

A-)Risk Triggers

B-)Unmanageable Risks

C-)Residual Risks

D-)Accepted Risks

Answer is C. Residual risks that are expected to remain after planned responses have been taken, as well as those that have been deliberately accepted.

Knowledge Area: Risk Management

PMP Exam Questions #36

You are working as a project manager in a company. You have the highest degree of authority, you are working full-time for your project and you manage the budget of the project. What is the organization structure in your company?

A-)Strong Matrix

B-)Projectized

C-)Functional

D-)Balanced Matrix

Answer is B. In a projectized organization structure, project manager has the highest level of authority, works full-time and manages the budget of the project.

Knowledge Area: Organizational Influences and Project Life Cycle

PMP Exam Questions #37

You are the project manager of a software project team consisting of 2 analysts, 4 software developers and 3 test engineers. One new test engineer will join the team in two weeks. What will be the number of communication channels after new test engineer joins the team?

A-)55

B-)50

C-)45

D-)36

Answer is A. The total number of potential communication channels is n(n-1)/2, where n represents the number of stakeholders.

Your team has 10 team members already (2 analysts, 4 software developers, 3 test engineers, and you as a project manager). After new test engineer joins, there will be 11 team members.

Number of communication channels = 11*(11-1)/2=11*10/2 = 55

Knowledge Area: Communications Management

PMP Exam Questions #38

All of the following are tools and techniques that can be used in Identify Stakeholders process EXCEPT:

A-)Expert Judgment

B-)Stakeholder Register

C-)Meetings

D-)Stakeholder Analysis

Answer B. Stakeholder analysis, Expert Judgment and Meetings are tools and techniques that can be used in Identify Stakeholders process. Stakeholder Register is an output of Identify Stakeholders process.

Knowledge Area: Stakeholder Management

PMP Exam Questions #39

The seller`s project is undertaken on contract and you are an employee of the seller. Since you earlier worked with XYZ Factory, the buyer, you happen to be aware of the evaluation criteria used in XYZ Factory to select sellers. You understand that this could be a potential conflict of interest situation. How do you propose to act?

A-)Do nothing and continue to work as before

B-)Take appropriate person in XYZ Factory into confidence and discuss this issue with her

C-)Disclose the evaluation criteria to your (seller) organization and help their business growth

D-)Remove yourself from the project

Answer is B. Since the evaluation criteria are proprietary information of XYZ Factory, it is important for you to discuss the matter directly with the appropriate person in the XYZ Factory.

Knowledge Area: N/A

PMP Exam Questions #40

During project planning phase, which of the following steps come latest compared to others?

A-)Hold kick-off meeting

B-)Gain formal approval of the plan

C-)Develop Budget

D-)Develop Schedule

Answer is A. Following is the order of steps in planning phase:

  • Develop schedule
  • Develop budget
  • Gain formal approval of the plan
  • Hold kick-off meeting
  • Kick-off meeting is the last step of planning phase.

Knowledge Area: N/A

Download Master of Project Academy PMP Question Bank (FREE)

See a PMP Sample Exam.

How to Get PMP Certification article describes the five major steps you should pass for getting PMP certification.

Check our PMP Exam Questions & Answers Video

PMP Questions and Answers