Trusted by 50,000+ professionals in 180+ countries, Master of Project Academy will help you to ace your professional career.

Critical Chain Method

4 Steps for Applying Critical Chain Method2 min. read

During Develop Schedule process, which is the 6th process of Time Management Knowledge Area, the outputs of the Time Management processes occurred before are organized and the final schedule of the project is produced. This is the key output of Develop Schedule process. After the schedule is created, it’s time to analyze it!  So that’s why the schedule network analysis will begin afterwards. And as listed in it the PMP training course, it may take multiple forms or it may be applied with different analysis methods. These methods are called Critical Path, Schedule Compression, What-if Scenario Analysis, Resource Leveling and Critical Chain Method. Critical Chain method, which is abbreviated as CCM, is the last technique used for schedule network analysis. In this article, we are going to learn what Critical Chain Method is all about.

Critical Chain Method vs Critical Path Method

Now, as you may have guessed from its name, Critical Chain Method is related to Critical Path Method. Before describing what Critical Chain Method is, let’s briefly remember what Critical Path method was. After we have defined the relationship of project activities, we were then connecting these activities to create the network schedule of the project. Then the last step was to determine the longest path to find critical path.

Critical Chain Method was developed by Eliyahu M. Goldratt. The approach of CCM is different than Critical Path. Let’s see how these two methods differ.

In the Critical Chain Method, a network diagram is created first. Then the second step is to develop the schedule by assigning each activity to occur as late as possible to still meet the end date. The third step is adding the resource dependencies. Finally, the critical chain is calculated.

Critical Chain Method

Critical Chain Project Management Advantages

But why using Critical Chain Method? What are the benefits? As we know, you will not have unlimited project resources in a project. These resources might be people, equipment, or physical space, etc. Even if there is not a mandatory dependency between the activities, sometimes the same resource may perform the activities. So this creates a dependency between the resources. This is why all of these dependencies must be considered in critical chain method as well.

Note that, in this method, the buffers should be added to critical tasks. What’s the objective of doing that? Because if there are risks that may cause project activities to take longer, these must be reflected in planning to create a realistic and attainable schedule.

Critical Chain Method

Leave a Reply

Your email address will not be published. Required fields are marked *

Master of Project Academy delivered online courses to more than 50,000 participants in more than 180 countries around the world. All courses are 100% Online, Self-Paced and 30 Day Money Back Guaranteed.


Master of Project Academy course portfolio includes but not limited to:


To learn more, visit our course portfolio.