CAPM Questions and Answers

FREE CAPM Questions and Answers | Assess Your Readiness Before CAPM Exam

17 min. read

CAPM or Certified Associate in Project Management is one of the world’s most prestigious certification in the project management field given by the Project Management Institute. CAPM certification exam has 150 questions and requires a good CAPM study plan to pass the exam successfully. Making practice with CAPM questions and answers before the exam as much as possible is the key to passing the CAPM certification exam.

Participants who have less than 5 years of experience: 38.60% increased their salary by 10% or more and 21.93% increased their salary by 20% or more.

For your CAPM exam prep, when practicing CAPM questions and answers, or taking a CAPM practice test, write down notes, especially for the mistakes you make. Then, go back to the related project management knowledge area and reread the topic to strengthen your knowledge.

Hint: You must check our 100% FREE CAPM Study Guide to pass the CAPM exam on your first attempt. This study guide has been prepared with the experience of teaching 100,000 professionals.


After helping over 500,000 professionals in more than 180 countries with a 99.6% first attempt pass rate, we have prepared a seven-step CAPM study plan. Read this CAPM study plan and create your own CAPM prep plan accordingly.


Do you want to hear what our students say about our CAPM courses? You can watch this video!

We will go through 20 CAPM questions and answers in this post. We will be giving rationales for each CAPM question and answer. You will see the relationship of each CAPM question and answer with the project management knowledge areas of PMBOK.

CAPM questions and answers

CAPM Certification Exam Questions and Answers #1

A manager and the head of engineering discuss a change to a major work package. After the meeting, the manager contacts you and tells you to complete the paperwork to make the change. This is an example of:

A-) Management attention to scope management.

B-) Management planning.

C-) A project expediter position.

D-) A change control system.

 

The answer is C. In this situation, the project manager acts as the secretary of the project and does the paperwork. So this is an example of a project expediter position where the project manager does not have any authority and power. The project manager does only paperwork.

Knowledge Area: Organizational Influences and Project Lifecycle

Your entry could not be saved. Please try again.
We sent links to your email! You should have received an email from us already. If you did not receive, make sure you check your spam folders and add masterofproject.com to safe senders list to receive our emails.

100% FREE CAPM® Pack

Let us send you links for our Free CAPM Pack. Package includes:

- CAPM Question Bank
- CAPM Flash Cards
- CAPM Prep Book Sample PDF
- Free CAPM Overview Training
- CAPM Cheat Sheets & more

CAPM Practice Questions and Answers #2

During a team meeting, a team member asks about the measurements that will be used on the project to judge performance. The team member feels that some of the measures related to activities assigned to him are not valid measurements. The project is BEST considered in what part of the project management process?

A-) Initiating

B-) Executing

C-) Monitoring & Controlling

D-) Closing

The answer is B. Executing. The question states that the team member feels some of the measures on his activities are not valid. Therefore, he must be working during the executing phase of the project where project deliverables are produced and project members perform most of the work they should do.

Knowledge Area: Project Management Processes


Attend our 100% Online & Self-Paced One-Hour Free CAPM Training.

Free CAPM Training


CAPM Questions and Answers #3

Your company just won a major new project. It will begin in three months and is valued at 2m USD. You are the project manager for an existing project. What is the FIRST thing you should do once you hear of the new project?

A-) Ask management how the new project will use resources

B-) Resource level your project

C-) Crash your project

D-) Ask management how the new project will affect your project

The answer is D. Ask management how the new project will affect your project. Since this is another project that your company is going to execute, you need to be sure whether it will impact your project.

Knowledge Area: Integration Management Knowledge Area

Watch our “CAPM® exam questions and answers” video

CAPM Certification Exam and Answers #4

You are a new project manager who has never managed a project before. It would be BEST in this situation to rely on _____ during planning in order to improve your chance of success.

A-) Your intuition and training

B-) Stakeholder analysis

C-) Historical information

D-) Configuration management

The answer is C. Historical information. The first thing to explore before starting a new project is the historical information about similar projects in the organizational process assets library of the organization.

Knowledge Area: Integration Management Knowledge Area

CAPM Questions and Answers #5

During project execution, a team member comes to the project manager because he is not sure of what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of work packages?

A-) WBS Dictionary

B-) Activity List

C-) Project scope statement

D-) Scope management plan

The answer is A. WBS Dictionary. Work packages in a Work Breakdown Structure contain only nouns or a couple of words regarding work or deliverable. Detailed information on what needs to be done, responsible, prerequisites, successors, due date, etc. are included in the Work Breakdown Structure Dictionary.

Knowledge Area: Scope Management Knowledge Area


Enroll in our CAPM exam simulator once you complete your CAPM study. You can take a look at Free CAPM Exam Simulator Demo.


CAPM Questions and Answers #6

During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by these stakeholders. The BEST thing for the project manager to do is to:

A-) Let the sponsor know of the stakeholders’ requests.

B-) Evaluate the impact of adding the scope.

C-) Tell the stakeholders the scope cannot be added.

D-) Add the work if there is time available in the project

schedule

The answer is C. Tell the stakeholders the scope cannot be added. After the scope of a project is finalized and the scope baseline is determined, it can be changed only with the approved changed requests. If there is not an approved change request, the existing scope baseline must be valid and the project team must work on delivering that scope only. In the scenario, the scope is defined already but some stakeholders ask to add new work to the scope. This cannot be done unless there is an approved change request. Therefore, stakeholders must be informed that this new work cannot be added.

Knowledge Area: Scope Management Knowledge Area

CAPM Questions and Answers #7

Your project management plan results in a project schedule that is too long If the project network diagram cannot change but you have extra personnel resources, what is the BEST thing to do?

A-) Fast track the project.

B-) Level the resources.

C-) Crash the project.

D-) Monte Carlo analysis.

The answer is C, crash the project. Because, in the first sentence, it is mentioned that the schedule is too long, therefore the aim is to make a shorter schedule. And in the second sentence, it is mentioned that you have extra personnel resources. If you have resources, you can put more resources into an activity to complete it in a shorter time. And this is actually a description of crashing an activity or crashing the project. If you look at the other options, fast-tracking was performing activities in parallel instead of series, therefore it is irrelevant. Leveling the resources was for fixing the over-allocation of resources and distributing the tasks to all your resources uniformly. And Monte Carlo analysis was another estimating tool that is an irrelevant choice as well. Therefore, here the best answer is C.

Knowledge Area: Schedule Management Knowledge Area

CAPM Practice Questions and Answers #8

An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9, and a late finish (LF) of day 19. The activity:

A-) Is on the critical path.

B-) Has a lag.

C-) Is progressing well.

D-) Is not on the critical path.

The answer is D. is not on the critical path. Because if you look at the early start and late start values of the activity, you can find the float or the slack of activity’s time by subtracting the early start, 3 days, from the late start, 13 days. And it gives 10 days of float for this activity. You will find the same result if you go through subtracting the early finish, 9 days, from the late finish, 19 days. Since the float of the activity or the slack of the activity is greater than zero, it’s not on the critical path. Remember the critical path activities was having zero floats, therefore the answer is D.

Knowledge Area: Schedule Management Knowledge Area

CAPM Questions and Answers #9

Early in the life of your project, you are having a discussion with the sponsor about what estimating techniques should be used. You want a form of expert judgment, but the sponsor argues for analogous estimating. It would be BEST to:

A-) Agree to analogous estimating, as it is a form of expert judgment

B-) Suggest life cycle costing

C-) Determine why the sponsor wants such an accurate estimate

D-) Try to convince the sponsor to allow expert judgment because it is typically more accurate.

The answer is A. Agree to analogous estimating, as it is a form of expert judgment. Since analogous estimating is a type of expert judgment you can accept it. This is a tricky question.

Knowledge Area: Cost Management Knowledge Area

CAPM Questions and Answers #10

A schedule performance index, SPI, of 0.75 means:

A-) Project is over budget.

B-) Project is ahead of schedule.

C-) Project is progressing at 75% of the rate originally planned

D-) Project is progressing at 25% of the rate originally planned

The answer is C, the project is progressing at 75% of the rate originally planned. A is irrelevant because SPI is a schedule performance index. We cannot derive any conclusion about the budget performance of the project with this index. B is not correct because SPI is less than one, therefore, the project is behind schedule. And D, says that you have completed 25% of the work that you have originally planned, so it’s not correct. The correct answer here is C, because SPI 0.75 means, you have completed 75% of the work that you have originally planned.

Knowledge Area: Cost Management Knowledge Area

Enroll in our FREE CAPM course to learn more about CAPM Certification

CAPM Questions and Answers

CAPM Questions and Answers #11

You are the program-level manager with several project activities underway. In the executing process group, you begin to become concerned about the accuracy of progress reports from the projects. What would BEST support your opinion that there is a problem?

A-) Quality Audits

B-) Risk Quantification Reports

C-) Regression Analysis

D-) Monte Carlo Analysis

The answer is A. quality audits. If you read the second sentence again, it says that you are concerned about the accuracy of progress reports from the project. In order to check whether the standards of your organization have been applied in the projects that you are responsible for, you can conduct a quality audit and find out whether there is really a problem. Therefore, here the best answer is A, Quality Audits.

Knowledge Area: Quality Management Knowledge Area

CAPM Questions and Answers #12

You are a project manager for a major information systems project. Someone from the quality department comes to see you about beginning a quality audit of your project. The team, already under pressure to complete the project as soon as possible, objects to the audit. You should explain to the team that the purpose of a quality audit is:

A-) Part of an ISO 9000 investigation

B-) To check if the customer is following its quality process

C-) To identify inefficient and ineffective policies

D-) To check the accuracy of costs submitted by the team

How would you explain it to your team if you were in this case? The best answer is C, to identify inefficient and ineffective policies. B and D are irrelevant options because the quality audit is done in order to check whether you are meeting the quality standards, and whether you are following the quality procedures of your company. Therefore, it’s not related to whether the customer is following its quality processes. Or it is not related to the accuracy of costs submitted by the team.

Knowledge Area: Quality Management Knowledge Area

CAPM Questions and Answers #13

During every project team meeting, the project manager asks each team member to describe the work he or she is doing, and the project manager assigns new activities to team members. The length of these meetings has increased because there are many different activities to assign. This could be happening for all the following reasons EXCEPT:

A-) Lack of a WBS

B-) Lack of a responsibility assignment matrix

C-) Lack of resource leveling

D-) Lack of team involvement in project planning

The answer is C, lack of resource-leveling. If you read the clauses again, here the problem is the activities or the tasks that need to be performed in the project are not clear. So, the reasons for these ambiguities, or these unclear points about the tasks that will be performed can be the lack of a WBS. If you could not decompose your project activities and the creation of WBS, then this might be causing ambiguities in your project tasks. Also, if you do not have a clear and concise responsibility assignment matrix, then the resources of your project will have unclarity about who will do what in the project. Also, if the team was not involved in project planning, maybe you could not have identified the required steps, required tasks, and activities that need to be performed in the project. So, options A, B, and D are the possible reasons for this case mentioned in the question. However, lack of resource leveling might be causing a scheduling problem. Resource leveling is a technique used in the schedule management knowledge area, which was enabling the uniform distribution of tasks and activities in a project.

Knowledge Area: Resources Management Knowledge Area


Enroll in our CAPM exam simulator once you complete your CAPM study. You can take a look at Free CAPM Exam Simulator Demo.


CAPM Questions and Answers #14

Conflict resolution techniques that may be used on a project include confronting, smoothing, forcing, and:

A-) Withdrawing

B-) Directing

C-) Organizing

D-) Controlling

Which of the options is a conflict resolution technique? The answer is A, Withdrawing, or in other words, avoiding. The other three are directing, organizing, and controlling, which are not types of conflict resolution techniques. Therefore, the answer is A.

Knowledge Area: Resources Management Knowledge Area

CAPM Exam Questions and Answers #15

All of the following about communication models are true EXCEPT:

A-) The sender encodes his thoughts and sends them to the receiver.

B-) Information is sent by the sender to the receiver with the assistance of the medium.

C-) The receiver acknowledges if he agrees with the information he received.

D-) The message is decoded by the receiver into thoughts.

Which one is not correct about communication models? The answer is C, Receiver acknowledges if he agrees with the information he received. If you remember, the acknowledgment was saying that the receiver got the message, but it does not mean that he or she agrees with the received message. Acknowledgment means only that the message sent by the other party has been received. Therefore, it does not mean an agreement, and here the best answer is C.

Knowledge Area: Communications Management Knowledge Area

CAPM Questions and Answers #16

A project manager is quantifying risk for her project. She needs an expert opinion in this process and related experts are spread over to different geographical locations. How can she continue?

Using Monte Carlo analysis online

Applying the critical path method

Determine options for recommended corrective action

Applying the Delphi Technique

The answer is D, applying the Delphi Technique. If you remember from our previous lectures, that technique was asking the expert’s opinion on a topic or on a problem and collecting their feedback anonymously, and then sending the results back to the experts again, and recollecting their responses again. And reiterating this process until a consensus is reached by all participants, by all experts. Therefore, since expert opinion is important for this case and experts are spread over different geographical locations, we can use Delphi Technique.

Knowledge Area: Risk Management Knowledge Area

CAPM Exam Questions and Answers #17

During risk management activities, 236 risks have been identified which are caused by 13 root causes. You could eliminate the 234 risks through your risk management activities. For the remaining 2 risks, you, together with your team, could not find a way to mitigate or insure the risks. Also, these 2 risks cannot be outsourced or removed from the project scope. What is the best solution?

A-) Accept the risk

B-) Mitigate the risk

C-) Avoid the risk

D-) Transfer the risk

The answer is A, accepting the risk. When you read the case, the project manager tried first to eliminate the risk, then tried to mitigate or insure the risk. But all these options did not work. And the last step is the risk should be accepted by the project team and continuous reserves should be allocated in order to accommodate risks or in order to overcome the bad impacts of these risks when they occur. Therefore, the best answer here is to accept the risk and also plan contingency reserves.

Knowledge Area: Risk Management Knowledge Area

CAPM Questions and Answers #18

The project team is arguing about the prospective sellers who have submitted proposals. One team member argues for a certain seller while another team member wants the project to be awarded to a different seller. The BEST thing the project manager should remind the team to focus on in order to make a selection is the:

A-) Procurement documents

B-) Procurement audits

C-) Evaluation criteria

D-) Procurement management plan

The answer is C, evaluation criteria. The source selection criteria or evaluation criteria defined in the plan procurement management process actually defines, in an objective way, how quantitatively, the potential sellers will be evaluated in conduct procurements process. Therefore, if you have applied specific metrics, specific categories to evaluate, or assess a potential seller in the conduct procurement process, then you have to use those metrics, use those categories to evaluate each seller one by one. And the sellers, which got the highest scores should be awarded the contract. Therefore, the team members should not go into arguments about the selection of the sellers. Because you have already a quantitative metric to evaluate which seller is the best matching your source selection criteria.

Knowledge Area: Procurement Management Knowledge Area

CAPM Questions and Answers #19

A project manager is in the middle of creating a request for a proposal (RFP). What part of the procurement process is she in?

A-) Conduct procurements

B-) Plan Procurements

C-) Control Procurements

D-) Close Procurements

The answer is B, she is in the plan procurements process. Because procurement statement of work, procurement documents are prepared in the plan procurements management process. An RFP is a procurement document as well. Therefore, it is prepared in the plan procurements process. RFP was defining what the buyer is requiring from the seller.

Knowledge Area: Procurement Management Knowledge Area

CAPM Questions and Answers #20

You want to group your project stakeholders based on their authority and involvement in the project. Which of the following is an appropriate model for this?

A-) Power/Interest Grid

B-) Power/Influence Grid

C-) Influence/Impact Grid

D-) Salience Model

The answer is B. Power/Influence Grid. The Authority of a stakeholder represents the power of the stakeholder and the involvement of a stakeholder represents the influence level of the stakeholder. Therefore, the answer is B. Power/Influence Grid.

Knowledge Area: Stakeholder Management Knowledge Area

CAPM Questions and Answers

You might want to check our CAPM Exam Questions post as well.

2 thoughts on “FREE CAPM Questions and Answers | Assess Your Readiness Before CAPM Exam

Comments are closed.