Trusted by 50,000+ professionals in 180+ countries, Master of Project Academy will help you to ace your professional career.

estimate activity durations

What Has To Be Done In Estimate Activity Durations Process?3 min. read

If you already took a PMP training course, you must know how the schedule is planned in plan schedule management process, how activities are defined in define activities process, the order of activities in sequence activities process, and resource requirements for activities in estimate activity resources process. If you haven’t started to prepare for the PMP exam yet, don’t forget to include this important process in your PMP study plan! Because PMP exam training explains all these processes of Time Management. After these processes, Estimate Activity Durations Process begins. In this article, we are going to explore what Estimate Activity Durations Process is all about. Also, give an example of Estimate Activity Durations Process. 

What is Estimate Activity Durations Process?

The Estimate Activity Durations is the process of estimating the number of work periods needed to complete individual activities with estimated resources. After activity resources are determined, these resources estimate the activity durations. How long they need to complete an activity. Based on their estimations, overall project duration will be determined respectively.

estimate activity durations

What is Done in the Estimate Activity Durations Process?

During Estimate Activity Durations process amount of time that each activity will take places is estimated. Based on the description and details of the task, assignee of the activity makes an estimation. Each activity duration is estimated similarly by the assignee of each activity.

Before estimation, if there are ambiguities or unclear points about an activity, the estimation will have padding. In order to understand this, let’s see what padding is first.

estimate activity durations

What is Padding?

Pad is extra time or cost added to an estimate because the estimator does not have sufficient information about the activity. During estimate activity durations process, project resources make their estimations based on the currently available information today. And if there is not that much information about the activity, or if there are risks that may arise and cause the activity to take longer, this will cause padding during estimation.

Therefore the project manager should find ways to make each activity as clear as possible to make accurate estimates in the estimate activity durations process. Any risks might be eliminated as much as possible. Unclear points or missing information about the activities must be cleared out to have a more accurate estimation of the project resources.

estimate activity durations

Although the project manager tries to eliminate risks, there might be still existing risks that must be taken into account. In this case, if there is a need for a pad, it should be addressed through risk management. Because reserves to accommodate risks when they occur are planned during risk management activities. During Estimate Activity Durations process, project resource must consider only the activity duration if everything goes as planned.

Estimate Activity Durations Process Example

There are many techniques used in Estimate Activity Durations Process. Typically, one technique is chosen and used for all activity duration estimations in a project.

estimate activity durations

In our Estimate Activity Durations process example, we used Beta Distribution of PERT analysis.

As you see, optimistic, pessimistic and most likely activity duration estimates for each activity are taken from the estimator. When we substitute these optimistic, pessimistic and most likely values in the beta distribution formula of PERT analysis,

  • Estimated activity duration for analysis of invoice screen is 8.67 days.
  • Estimated activity duration for the design of invoice screen is 7.50 days.
  • Estimated activity duration for the development of invoice screen is 11.17 days.
  • And estimated activity duration for the test of invoice screen is 5.17 days.

These estimated activity durations are used to calculate the total project duration and complete the schedule of the project as well.

Estimate Activity Durations

 

Master of Project Academy delivered online courses to more than 50,000 participants in more than 180 countries around the world. All courses are 100% Online, Self-Paced and 30 Day Money Back Guaranteed.


Master of Project Academy course portfolio includes but not limited to:


To learn more, visit our course portfolio.