The best project decision you’ll make this year is the one you don’t take.
Four posts on how estimates get cursed. It’s fair to ask what the cure actually is.
In auction theory the answer is uncomfortable. The only real defense against the winner’s curse is to bid in a way that means you lose more often. Disciplined bidders win fewer auctions and make more money. The undisciplined ones win a lot and go broke.
Applied to projects: fewer projects, better projects, and a willingness to walk away. From a bid you could win. And from a project you’ve already started.
Optimism Bias in Project Management: Why Your Best Business Case Is the Most Dangerous One
Why is the willingness to lose the whole cure?
Because every technique in Part 4 only works if you’re prepared to act on the answer.
The reference class says the honest estimate loses the bid? Then you lose the bid. The three-point estimate says the date can’t be met? Then you don’t promise it. The premortem says the business case doesn’t survive contact with adoption? Then you don’t submit it.
An organization that can’t tolerate losing a bid will, structurally, win cursed ones. There’s no estimating technique that fixes an incentive. The same is true of people. If you can’t bear to be the PM who said “Q3” while someone else said “Q2,” you’ll keep saying Q2.
How do you make the bid/no-bid decision a real one?
Most bid/no-bid reviews are a formality held after the decision to bid has already been made. The proposal team is assembled, the deadline is on the calendar, and the review’s job is to say yes.
The fix is to set the criteria and the threshold before the RFP arrives, score every opportunity against them, and let a low score mean no. The criteria that matter:
- Strategic fit. Does winning move us where we want to go, or just keep people busy?
- Delivery capability. Do we have the people now, or would we be hiring into a contract we’ve already priced?
- Requirement clarity. Do we understand the work well enough to price it? If not, we’re guessing, and the winner’s curse rewards the worst guess.
- Relationship. Do we know the buyer, or are we column fodder for a decision already made?
- Selection basis. If price is the only criterion, the winner will be cursed. Decide in advance whether you want to be.
- Margin at a realistic estimate. Not at the estimate that wins. At the one the reference class says is true.
- Risk exposure. What’s the worst case, and can we survive it?
- Opportunity cost. If we win, what don’t these people do instead?
Unrealistic Project Deadlines: The PM Who Said Yes Fastest
What is the sunk cost fallacy in project management?
Money and time already spent are gone regardless of what you do next. Only future costs and future benefits should drive the decision. Everyone knows this. Almost nobody acts on it, for four reasons:
- Escalation of commitment. Each additional investment makes stopping feel more expensive, even though it’s less.
- Reputation. It’s “my project.” Stopping it looks like admitting the approval was wrong.
- “We’ve come this far.” Progress toward a destination that no longer makes sense is still just distance.
- Nobody set a stopping rule. So every review defaults to continuing, because continuing requires no decision.
The reframe that helps: cancelling doesn’t waste the money you’ve spent. That money is spent whether you continue or not. Continuing wastes the money you haven’t spent yet.
How to Use the 5 Whys Technique at Work (Step-by-Step With Examples)
| Walking away isn’t the project failing. It’s the project succeeding at its last job: telling you the truth. |
Kill criteria: decide how you’ll stop before you start
At approval, write down the evidence that would cause you to stop. Benefit assumptions that fail a defined test. Cost-to-complete exceeding remaining benefit. A strategic priority that shifts. A key dependency that falls through.
Then set the gate dates and give the gates real authority. A stage gate that can’t say no is a status meeting. Pre-committing to criteria changes what the later decision is about: evidence instead of people. It also protects the sponsor, who can now cancel a project by pointing at a rule they set rather than at a team they picked.
Embracing Failure: How Project Managers Can Transform Setbacks into Stepping Stones
When should you cancel a project?
- The business case no longer holds under current assumptions, and nobody has re-run it.
- The remaining cost to complete exceeds the remaining benefit.
- The organization’s priorities changed and the project was never re-tested against them.
- A key assumption was disproven and the plan was patched instead of re-decided.
- The team is delivering the plan on schedule, and nobody can point to the value.
- The argument for continuing rests on what’s already been spent.
One of these is a conversation. Three of them is a decision.
How do you say it to the sponsor?
Frame it as a reallocation, not a funeral. “Continuing costs this much more for this much benefit. Stopping here saves the difference, and here’s what that money could fund instead.” Bring the alternative use. A sponsor can defend moving budget to a better project far more easily than they can defend a cancellation with nothing on the other side.
Bring the salvage too: what was learned, what was built that can be reused, which risks are now understood. And do it early. Cancellation gets more expensive every month, and the sponsor’s willingness to hear it goes down at the same rate.
The series, in one paragraph
Whenever several estimates compete and the most extreme one wins, the winner is the one who was most wrong. That’s how the lowest bid becomes the most expensive vendor (Part 1), how the best-looking business case becomes the biggest overrun (Part 2), and how the PM who said yes fastest ends up explaining month five (Part 3). The estimating toolkit, reference classes, honest three-point estimates, defended contingency, and the premortem, gives you the true number (Part 4). And this post is about what the true number is for: the willingness to lose the auction when losing is the right answer.
Frequently asked questions
What should be in a bid/no-bid checklist?
Strategic fit, delivery capability, requirement clarity, relationship with the buyer, whether price is the sole selection criterion, margin at a realistic rather than a winning estimate, worst-case exposure, and opportunity cost. Score each before the RFP arrives and set the threshold in advance.
How do you overcome the sunk cost fallacy on a project?
Separate the decision from the history. Compare remaining cost to remaining benefit only, set kill criteria at approval so stopping is a rule rather than a judgment about people, and frame cancellation as moving budget to a better use.
Who has the authority to cancel a project?
Usually the sponsor or the steering committee, through a stage gate. The project manager’s job is to bring the evidence and the recommendation, clearly and early, even when the recommendation is to stop.
| WHERE THE NEW PMP® EXAM TESTS THIS
Business case validation, benefits realization, and closure decisions are Business Environment territory: 26% of the PMP® exam since July 9, 2026, tripled from 8%. Expect case-study sets where the correct answer is to recommend stopping, and distractors that reward continuing because of what has already been invested. The exam is testing whether you can lose the auction on purpose. |
| The exam tests judgment now. Practice it with an instructor.
Deciding whether to bid, whether to continue, and how to tell a sponsor: these are the scenarios the PMP® exam has asked since July 9, 2026, and the ones our instructors work through live. The PMP® Online Class runs four days and 35 contact hours, mapped to the current exam and the PMBOK® Guide 8th Edition. The Pro plan adds a one-hour one-on-one PMP® coaching session after the class. |